12:43 - 16.11.2020
November 16, Fineko/abc.az. In the first three quarters of 2020 about $399 million in operating expenditure and about $1,398 million in capital expenditure were spent on ACG activities, ABC.AZ informs with a link to BP’s report.
During the third quarter, fabrication activities on the topsides and drilling facilities for the Azeri Central East (ACE) platform continued at the fabrication yard in Bibi-Heybat.
"The latest activities include the commencement of the major lift programme despite the disruption caused by COVID-19, the arrival of the drilling derrick at the yard, with all three sections of the derrick already safely offloaded from the barge and positioned at the site’s construction location. Construction of the drilling modules is currently ongoing. At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF) the pin piles have been completed, successfully loaded out and driven into the seabed ready to receive the platform jacket. The jacket fabrication continues, as does the work on the subsea structures," the report says.
15 July 2026
15 July 2026
14 July 2026
13 July 2026