12:42 - 7.09.2026
September 7, Fineko/abc.az. The Directorate of Facilities under Construction has summed up the results of two major tender procedures for the construction of water supply and sewerage systems in areas liberated from occupation.
According to the procurement results, contracts for totally 19.18 million manats were concluded with the winner companies. The projects will cover a number of settlements in the Aghdam and Jabrayil districts.
Agdam district (13.88 million manats):
The construction of water supply and sewerage systems in Garvend and Eyvazkhanbeyli villages will be carried out by T.T.Ş.-Inşaat LLC. The total cost of the contract is 13.884 million manats.
Jabrayil district (5.29 million manats):
Hydro-Geo Environment Group LLC became the winner of the tender for the construction of external water supply and sewerage systems for the villages of Soltanli, Mashanli, Boyuk Marjanli and Saryjaly. The parties signed an agreement in the amount of 5,297,505 manats.
Implementation of these projects is carried out as part of the restoration of the infrastructure of the liberated territories and preparations for the Great Return of the population.