IGB pipeline to be commissioned on time

18:06 - 5.04.2022


April 5, Fineko/abc.az. 90-95% of works have been done within the framework of construction of 182 km Interconnector Greece – Bulgaria – IGB to transport Azerbaijan's natural gas to Bulgaria.

ABC.AZ reports that construction of the gas pipeline will be completed on time (commission date, scheduled for the last time - July 2022) and gas will be supplied from Greece to Bulgaria via the line at the beginning of July.

The construction of the IGB pipeline is up to an end.

In connection with the postponement of the commissioning of the Greek-Bulgarian connecting gas pipeline, the commissioning of which was scheduled for the end of 2020, Azerbaijani gas is temporarily transported to Bulgaria via a connecting line on the border with Greece (Kula-Sidirokastro).